pasteurized milk curd and whey mixture cheddarised curd cooked and one side formed product cooked and two sides formed product cooled product packed product
The milk which has been standardised and pasteurised at 65°С is fed from the milk treatment sector into DONI®Double O Vat PF/1/. The coagulation, cutting and drying of the curd grain are automated and follow the production parameters of this type of manufactured cheese.
The curd-whey mixture is transported in the module DONI®Cheddarmatic/2/ for further draining and cheddaring. The process runs in a controlled environment for around 40 min. The cheddared curd is cut into pieces at the outlet with a pneumatic guillotine which are then fed into DONI®Plastformer/3/ for processing.
The cooked product is automatically filled into block moulds which are placed on a draining plate. They stay on the conveyor belt for a minimum period of 5 minutes to allow for one sided moulding and then they are rotated by180° with DONI®Rotomatic PF/4/.
The ascending conveyor belt DONI®Transup/5/ stacks them on mobile stacks DONI®Transcarriage/6/ which are manually transported into a refrigeration chamber for cooling to 12°-15°С. The cooling process continues for 2 to 12 hrs, depending on the moulds weight.
Once the product is cooled the mobile stacks are manually transported to the descending conveyor belt DONI®Transdown/7/ The block moulds are taken to DONI®Mouldmatic PRD/8/, where the finished product is removed from the mould and sent for packaging/10/. The block moulds are rotated on DONI®Rotomatic PF/4/ and then transported for tunnel cleaning/9/. After one more rotation they are ready for refilling.
This production line is suitable for medium and large dairy factories. The 24 hr production output of the line can reach up to 40 000 kg finished product, depending on the weight of the moulds. The process is fully automated apart from the cooling process.